Original budget
45.23 Cr
45,23,26,593
Budget Master line-item total
| Date | Project day | Approved actual | Run-rate budget | Variance |
|---|---|---|---|---|
| 2026-03-19 | 414 | ₹-0.059 Cr | ₹0.087 Cr | −₹0.147 Cr |
| 2026-03-20 | 415 | ₹0.020 Cr | ₹0.087 Cr | −₹0.068 Cr |
| 2026-03-21 | 416 | ₹0.002 Cr | ₹0.087 Cr | −₹0.086 Cr |
| 2026-03-22 | 417 | ₹0.027 Cr | ₹0.087 Cr | −₹0.060 Cr |
| 2026-03-23 | 418 | ₹0.000 Cr | ₹0.087 Cr | −₹0.087 Cr |
| 2026-03-24 | 419 | ₹0.001 Cr | ₹0.087 Cr | −₹0.086 Cr |
| 2026-03-25 | 420 | ₹0.001 Cr | ₹0.087 Cr | −₹0.086 Cr |
| 2026-03-26 | 421 | ₹0.001 Cr | ₹0.087 Cr | −₹0.087 Cr |
| 2026-03-28 | 423 | ₹0.001 Cr | ₹0.087 Cr | −₹0.086 Cr |
| 2026-03-29 | 424 | ₹0.006 Cr | ₹0.087 Cr | −₹0.081 Cr |
| 2026-04-05 | 431 | ₹0.001 Cr | ₹0.087 Cr | −₹0.086 Cr |
| 2026-04-17 | 443 | ₹0.001 Cr | ₹0.087 Cr | −₹0.086 Cr |
| 2026-04-30 | 456 | ₹0.004 Cr | ₹0.087 Cr | −₹0.083 Cr |
| 2026-05-18 | 474 | ₹0.002 Cr | ₹0.087 Cr | −₹0.085 Cr |
| Total to date (all expense days) | 516 | ₹49.13 Cr | — | — |